Lead Contractor Kumho Construction (50%), Joint Contractors Namyang Construction (25%)

Haedong Construction (20%), Donglim General Construction (5%)

Suncheon City, Jeollanam-do (Mayor Noh Gwan-gyu) announced on the 2nd that Kumho Construction Co., Ltd. has been selected as the construction company to carry out the building construction for the new city hall project.


The city proceeded with the selection process through a technical bid method (detailed design technical proposal bidding). Two consortia, Gyeryong Construction Industry Co., Ltd. and Kumho Construction Co., Ltd., participated, and on July, the Public Procurement Service evaluated the technical proposals submitted by each company and then combined the scores with the previously submitted price scores to determine the final evaluation.

Bird's-eye view of the new city hall <span class="photo-credit">Photo by Suncheon City</span>

Bird's-eye view of the new city hall Photo by Suncheon City

View original image

The city reviewed the technical proposals presented by the Kumho Construction Co., Ltd. consortium to decide on adoption, plans to sign the contract in early September, and aims to commence construction by November.


Following this, the construction will be carried out over two years, with the new city hall expected to be completed by the end of 2025, after which office relocation will be completed. The old city hall will be demolished by the second half of 2026, and a parking lot and park will be created to finalize the project.


Meanwhile, the city requested the Public Procurement Service in January to issue orders for electrical, communication, and fire protection works. The final selections were made with Woogwang ENC Co., Ltd. (electrical), Yoopung Information Technology Co., Ltd. (communication), and Changwon Gijeon Co., Ltd. (fire protection), with only contracts remaining to be signed.


The Suncheon City new city hall project plans to build a facility with a total floor area of 47,048㎡, consisting of one basement floor and six above-ground floors. The total project cost is 209 billion KRW, including 170.1 billion KRW for facility construction costs. The project site will be expanded eastward from the current city hall site.



Asia Economy Honam Reporting Headquarters, Reporter Heo Seon-sik hss79@asiae.co.kr