Overall Progress Rate of 2nd Industrial Complex at 90%... Complex Administrative Town at 80% and Agricultural-Industrial Complex at 74% Progress Rate Within the Year

Wanju-gun's Techno 2 Industrial Complex, Complex Administrative Town, and Agricultural Industrial Complex 3 Major Projects 'Smooth Progress' View original image


[Wanju=Asia Economy Honam Reporting Headquarters Reporter Kim Han-ho] Wanju-gun announced on the 4th that the three major development projects?the Wanju Technovalley 2nd General Industrial Complex, Wanju Small and Medium Enterprise Agricultural and Industrial Complex, and the Complex Administrative Town?are progressing smoothly according to the planned schedule.


According to Wanju-gun, the Wanju Technovalley 2nd General Industrial Complex development project is making all-out efforts, including applying to Jeonbuk Province at the end of last month for partial completion of Section 1 (1,869,000㎡).


This project involves investing a total of 392 billion KRW to develop an industrial complex covering 2,113,000㎡ in areas including Jenae-ri, Janggu-ri, Guam-ri, Dunsan-ri, and Yongam-ri in Bongdong-eup, with the current overall progress rate at 90%.


Wanju-gun has been conducting joint inspections of facilities for partial completion of Section 1 of the Wanju Technovalley 2nd General Industrial Complex, which will accommodate major companies such as Coupang, since June, and expects no significant difficulties in the completion of Section 1, attracting companies, and land sales.


The Wanju Small and Medium Enterprise Agricultural and Industrial Complex development project, with a total investment of 58.9 billion KRW, is also progressing without setbacks.


This project, developing 297,000㎡ in Seokjeon-ri and Sugye-ri of Samnye-eup and Guam-ri of Bongdong-eup, currently has a progress rate of about 74%, and it is known that negotiations for the sales disposition plan and additional sales announcements will take place within this month.


Wanju-gun is actively working on diversifying resident industry codes and subdividing small lots to improve convenience functions for companies intending to move into the agricultural and industrial complex, and plans to steadily proceed with the roadmap for roads, structures, and electrical work aiming for completion within the year.


The Complex Administrative Town, being developed on a 448,000㎡ scale around the county office in Ungok-ri, Yongjin-eup, is currently undergoing water pipe installation and reservoir expansion to achieve the target progress rate of 80% within the year.


The current progress rate of the Complex Administrative Town project, with a total investment of 99.3 billion KRW, is 48%. Bridge construction and riverbank protection works have already been completed, and underground works for city gas, electricity, and telecommunications have also been finalized.


Once the Complex Administrative Town is completed, it is expected to serve as a hub for regional development and stand as a new growth engine. Additionally, upon completion of the apartment construction project, about 4,600 residents will move into 2,010 households, establishing a new residential town.


Wanju-gun expects these three major projects to provide a groundbreaking turning point for regional development and the foundation of a self-sufficient city by attracting companies, creating jobs, and securing premium residential complexes.




Wanju=Honam Reporting Headquarters Reporter Kim Han-ho stonepeak@asiae.co.kr


This content was produced with the assistance of AI translation services.