Goal to Complete 3 Districts by November Next Year

Busan Port Authority (BPA, President Kang Jun-seok) is set to accelerate the development project of the Jinhae Yeondo Village relocation complex.


On the 13th, BPA announced that it will begin construction of the complex where residents from the relocation site will move, following the development of the West Container Terminal at Busan New Port.


The Yeondo Village relocation complex project involves creating a new residential complex for 51 households from Yeondo Village, Jinhae-gu, Changwon-si, Gyeongnam, which were displaced due to the construction of the West Container Terminal at the New Port.

Myeongdong 2 District.

Myeongdong 2 District.

View original image
Jaeun District.

Jaeun District.

View original image

BPA signed a consignment agreement with Changwon City and is carrying out the project divided into three districts (Myeongdong District 1, Myeongdong District 2, and Jaeun District).


Among these, the supply of relocation housing sites for 11 households in Myeongdong District 1 was completed in December 2021, providing the land. For Myeongdong District 2 with 19 households and Jaeun District with 21 households, after starting construction in July 2023, site offices and topsoil removal have been completed, and full-scale civil engineering work is scheduled to begin in December.


All infrastructure, including water and sewage, paving, and landscaping, will be completed by November next year, and after finishing the construction, the land will be provided to the relocated residents.



Kang Jun-seok, President of BPA, stated, “We will ensure the new residential complex for the Yeondo Village relocation plan is developed smoothly to provide conditions for the relocated residents to settle stably.”