Gwangju Buk-gu Office New Building 57.7% Complete... To Be Finished in January Next Year
The construction of the new building for Gwangju Buk-gu Office is progressing smoothly.
Aerial view of the new building of Gwangju Buk-gu Office. Provided by Gwangju Buk-gu Office
View original imageAccording to Buk-gu on September 3, the new office building being constructed on a 7,165-square-meter site in Yongbong-dong is scheduled for completion on January 26, 2026. Construction began in April last year, and the new building will have one basement floor and eight above-ground floors, housing office spaces for 17 departments, meeting rooms, a staff cafeteria, and a labor union office.
A total project budget of 30 billion won has been invested in this initiative. The site was secured by demolishing the existing annex on the left side of Buk-gu Office and the former Buk-gu Election Commission building. Once the new building is completed, the annex on the right side of Buk-gu Office will also be dismantled to improve the working environment for employees.
The Buk-gu Office building, constructed in 1985, is divided into five separate buildings, including the main building, public health center, and annexes, resulting in decreased work efficiency and significant inconvenience for residents. The long corridor layout also caused inefficient movement within the building. The building once received a "Grade C" in a detailed safety inspection, indicating the need for repairs and reinforcement. In addition, seismic reinforcement must be completed by 2035 in accordance with the earthquake disaster prevention plan.
Hot Picks Today
"Could I Also Receive 370 Billion Won?"... No Limit on 'Stock Manipulation Whistleblower Rewards' Starting the 26th
- Samsung Electronics Introduces New "Special Performance Bonus" for Semiconductors, Paid Entirely in Company Shares
- "From a 70 Million Won Loss to a 350 Million Won Profit with Samsung and SK hynix"... 'Stock Jackpot' Grandfather Gains Attention
- "US-Iran: Patch-Ups More Likely Than Settlement... Unlikely to Resolve Within 6 Months" [Economic Policy Zoom-In]
- "Who Is Visiting Japan These Days?" The Once-Crowded Tourist Spots Empty Out... What's Happening?
The current construction progress rate stands at 57.7%. Buk-gu plans to begin operations in the new building in the first half of 2026, in line with the regular personnel reshuffle scheduled for that period.