Hanwoolon Saeul Unit 3, Successful Ambient Pressure Test ... Verification of Nuclear Power Plant Equipment Manufacturing and Construction Technology Reliability
Korea Hydro & Nuclear Power (President Hwang Ju-ho) held a commemorative event on the 29th at the Saeul Units 3 and 4 construction site to celebrate the successful completion of the ambient pressure test, a major commissioning milestone for Saeul Unit 3.
Saeul Unit 3, which began the ambient pressure test on the 19th, confirmed the reliability of the manufacturing and construction technology of the reactor coolant system equipment, a core system of the nuclear power plant, with the successful completion of the test on the 25th.
The ambient pressure test is a critical test that applies 1.25 times the design pressure to the equipment and piping of the core system to verify the soundness and safety of the equipment, checking for leaks in all joints and connections within the reactor coolant system pressure boundary.
Hot Picks Today
Samsung Electronics Introduces New "Special Performance Bonus" for Semiconductors, Paid Entirely in Company Shares
- "Could I Also Receive 370 Billion Won?"... No Limit on 'Stock Manipulation Whistleblower Rewards' Starting the 26th
- Opening a Bank Account in Korea Is Too Difficult..."Over 150,000 Won in Notarization Fees Just for a Child's Account and Debit Card" [Foreigner K-Finance Status]②
- "From a 70 Million Won Loss to a 350 Million Won Profit with Samsung and SK hynix"... 'Stock Jackpot' Grandfather Gains Attention
- "Who Is Visiting Japan These Days?" The Once-Crowded Tourist Spots Empty Out... What's Happening?
Choi Il-kyung, Head of the Construction Business Headquarters, said, “In addition to the successful ambient pressure test, we will focus all our capabilities on subsequent processes to fulfill our role as an overseas business forward base, and we will thoroughly adhere to the basics and principles regarding safety and quality.”